Burlington Greenway and Island Line Trail - Construction Updates

Vermont summers... Warmer temperatures, flowers dotting the hillsides and the distant sounds of construction vehicles. 

Construction on South Hero's South Street Updates

South Hero's South Street is currently under construction. Ultimately, the project will span South Street from between Martin Rd. and Landon Rd., a total distance of about 1.3 miles.  The construction will take place in two phases. Phase 1 - will take place from Martin Rd to West Shore Rd. Phase 2 - will be taking place from West Shore Rd. to Landon Rd.  Expected completion date for Phase 1 is the end of July. Expected construction completion date of Phase 2 is late summer/early fall. Construction and detours are a bummer for biking but ultimately, the work that is being done now is going to make South Shore so much more accessible and comfortable for everyone (regardless of their mode of transportation) in the future. So thank you for your understanding and patience!

It is important to note that this information is being provided as a convenience and is intended for reference only.  Local Motion assumes no responsibility or liability for any loss or damage suffered as a result of reliance on or misuse of the information. For more information on the construction taking place, please visit www.southherovt.org/selectboard.

 

August 18 update

South_Hero_Detour_Map.jpg

South Street in South Hero is completely closed to through vehicle traffic between Landon Road and the Whipple/West Shore intersection during week days. South Street, when open, is passable by bike but sections are rough. Detours have been made to direct folks to East Shore Road via Whipple and Landon roads. We've made up a map of these detours, but please be aware that this map reflects what we've been told and may not 100% accurately reflect route availability.  

June 26 update

When construction begins between West Shore Rd. and Landon Rd, that section of Shore Street will be closed to traffic during daylight hours. South Street will open to traffic for evenings and weekends. During its closure, a detour will be provided directing people out Whipple Rd. to East Shore Rd. or from West Shore Rd. to Lakeview Rd.

 

May 22 update

Work began on April 25th on the section from Martin Rd. to West Shore Rd.

 


Burlington Lakeshore Bike Path Updates

The Burlington Department of Parks, Recreation & Waterfront (BPRW) is leading a full rehabilitation of the Burlington Greenway (informally known as the Lakeshore Bike Path).  Phase 1 of the project—from the ECHO Center to North Beach—was completed in December 2016.  Phase 2 of the project—from North Beach to the Winooski River bridge—will run from June through December of 2017.

Local Motion is working closely with BPRW and with other city officials to advise on detour design and management while the path is under construction.  We will post updates on both the status of path construction and on Local Motion's work related to construction detour planning on this page on a regular basis.  For more detailed updates on construction, visit BPRW's Phase 2 Updates page.

October 5th update

Screen_Shot_2017-10-05_at_10.21.46_AM.pngWe're doing a happy little dance - Phase 2a of the project is officially complete and can't wait to get out there and experience it! Phase 2b construction - from North Beach to Leddy Park has begun. It is expected that this construction will last through the end of the year. BPRW has released the official detour map over on their site and we've put together another one of our enhanced detour maps. Enhance detour signs are at the printers and soon to be deployed.

September 28th update

Bridge access is once again open and ready to be ridden!

September 26 update

Winooski River Bridge will be closed Sept. 27th! In order to complete the shoulder work along this section, Winooski River Bridge will be closed on Sept. 27th. 

September 22 update

Winooski Bridge Access is open! As promised, access to the Winooski River Bridge is open for the weekend. Shoulder works still needs to be completed along this section, but won't happen until next week - so in the meantime, get out there and enjoy it!

September 20 update

Winooski Bridge Closure. The section between north Ave Extension to Winooski Bridge has been been reduced to a single, flagged lane in preparation for shoulder work. 

  • North Ave Extension to Winooski River Bridge will be closed Sept. 21 for paving.
  • North Ave Extension to Winooski River Bridge will open the morning of Sept. 22nd and remain open for the weekend.
  • Further closures on this section of path can be expected next week.

September 6 update

Paving to begin Sept. 13th.  The gravel sub-base is being laid. The slopes are complete and seeding for re-vegetation has begun. between Staniford to North Ave Extension. Expect paving to begin on Sept. 13th.

August 25 update

Permits Approved! Pavement scheduled to begin on Sept. 12th. Pay extra attention at the intersections with North Ave Extension, Starr Farm Road and Staniford Road as gravel subbase will be making it's way to the path via these routes.

August 11 update

Dig! Dig! Dig! The Project scientist and VT DEC have given the go-ahead for full bike-path work to be completed between Staniford Road and Northshore. Excavation on this section had been limited until a plant inventory had been completed ensuring that the location of any endangered, rare or threatened species was known and all efforts to protect them were taken.

More signage! BPRW has added more detour signs as well as a number of safety banners along the detour. YAY! However, we have been hearing rumors of an individual in a blue SUV who has been taking down signage as well as harassing cyclists along the detour. The police are aware, but need a licence plate (or even better a video!) before they can take any sort of action. So if you're out and about and come across this individual, let us know. As always, even more information can be found on the BPRW's Phase 2 Updates page.

July 25 update 

Progress! Progress!  Slope work is nearly complete between Shore and Staniford Roads. Simultaneously, asphalt removal, tree protection, erosion control and prep work for grading is all taking place between North Shore to North Avenue Extension. The area in between is awaiting a visit from the Dept. of Environmental Conservation to make sure that construction activities will not detrimentally impact the vegetation along this section of the bike path. For a complete look at all the details, please visit visit BPRW's Phase 2 Updates page.

July 14 update   

Excavation to begin next week! The necessary vegetation has been cleared and some asphalt removal and initial rough grading has been completed. It has been brought to BPRW and Local Motion's attention that individuals are choosing to ride the bike path instead of using the detour. The detour has been set up for rider's safety and it is important, especially now as excavation is to begin in the coming days, that all bike path users are in fact using and following the detour. For even more details, including an update on the plants along the construction side and a sneak peek at the new pause place concepts, visit BPRW's Phase 2 Updates page.

 July 11 update

IMG_5856_(1).JPG

Local Motion has added additional signage to the bike path detour. A combination of messages of encouragement, safety tips, "you are here" maps and directional/way-finding assistance, we hope these signs will help people navigate the detour!

 

 June 22 update 

BPRW has released the official detour mapLocal Motion has updated it slightly to further lay out and identify the details and intricacies of the detour. At this time, Local Motion believes that the detour will be in effect until construction of this section of path is completed sometime in the coming fall.

June 12 update

Construction starts the week of June 19.  What section will be the first to be closed for construction is currently being negotiated with the contractor.  The only thing that is certain is that it will be in the northern section of the path (between North Beach and the Winooski River).  Local Motion is advocating for construction phasing that minimizes impacts on path users, particularly in the high tourist season.  

At least a portion of the detour will of necessity send bicyclists out onto North Avenue. The exact detour route is still being determined. Local Motion is evaluating the detour route carefully and working with the city to make it as safe and as direct as possible.  Again, we will share details as soon as they are available.

The Winooski River bridge will remain open until further notice.  At some point, the bridge will need to be closed for three to five days while the segment of path between North Avenue Extension and the bridge is repaved. Local Motion is advocating for holding off on this portion of the construction process until after Labor Day, when tourist traffic drops off and the Island Line Bike Ferry goes to weekend-only service.  Details to follow.  

 

June 5 update

Staging for construction on Phase 2 will begin during the week of June 12.  The path will remain open for the week, but path users should expect to encounter vehicles and personnel engaged in survey work and other preparations.  

 

May 19 update

Local Motion has submitted extensive comments to BPRW regarding detour routing, signage, and marketing.  We are meeting with BPRW staff next week to review those recommendations.

 

May 8 update

Local Motion has begun discussions with the Burlington Department of Parks, Recreation, and Waterfront on detour plans for the bike path during this summer's construction season.  Stay tuned for updates!


Follow Us